Background

A large and remote gold mine in Oceania sought a predictive maintenance solution to improve mobile fleet reliability and reduce unplanned breakdowns by identifying potential failures early. The team also aimed to extend component life through a consistent, data-driven approach, critical given the site’s isolation and potential supply chain disruptions.

In addition, the operation relied heavily on paper-based inspections and faced complex logistical challenges. They needed a solution that could digitize equipment inspections quickly, deliver measurable results, and be implemented without dedicated on-site resources.

Proposed Solution

Dingo’s implementation model enabled this large gold miner to transition from database setup to delivering Actionable Knowledge within weeks. The deployment process included:

1. Preparation and Planning – In mid-Q3 2024, a deployment plan was developed in collaboration with the site’s maintenance and reliability teams.

2. Installation and Integration – Following the purchase order in mid-Q3, Dingo configured the site, assets, and components in Trakka, then uploaded all pre-existing condition monitoring data. The Dingo team reviewed all historical data, established a new baseline, defined appropriate alert levels, and configured automated thresholds using the Dingo Rules Engine to ensure all future samples would be processed effectively. 

3. Training and Knowledge Transfer – Teams were trained on Dingo TRAKKA, the Dingo Mobile App, and reporting protocols. Site engagement was high, with over 1,400 platform interactions in the first month—covering inspections, data entries, and issue reviews. As part of the reporting protocols, monthly review meetings with site personnel were established to validate Breakdown Avoidance events and assess likelihood of avoided failures.

4. Go-Live and Issue Detection – With implementation completed, the site went live with Dingo in December 2024. The first Breakdown Avoidance event detected using Trakka was recorded on January 15—just 35 days after go-live—highlighting Dingo’s ability to deliver immediate value.

5. Ongoing Optimization – Regular asset review meetings between Dingo and the mine site team are ongoing and will continue to drive continuous improvement and asset health gains across the fleet. 

Results

By April, we had already achieved five major breakdown avoidances, with fault effects including high wear metals, fuel ingress, and dirt contamination across various equipment types, such as drills and hydraulic shovels, and components including engines, final drives, and more. The total value of avoided breakdowns reached $3.1 million, with 87% attributed to production savings and 13% to parts savings.

Breakdown Avoidance on Critical Production Asset

A standout result from the program was the early identification of a high-risk issue on a CAT 6060 Hydraulic Shovel, one of the site’s most critical production assets. With downtime costs nearing $20,000 per hour, a potential failure posed a significant financial risk. Leveraging TRAKKA’s predictive analytics, Dingo flagged a component issue that site experts later assessed as having a 100% likelihood of failure if left unaddressed. Timely intervention, informed by Dingo’s insights, prevented 60 hours of unplanned downtime, equating to more than $1 million in avoided production losses.

This outcome reinforces Dingo’s ability to deliver rapid, remote deployment of predictive maintenance solutions that drive tangible operational and financial value, protecting key assets, reducing risk, and unlocking significant cost savings in complex mining environments.

“When you’re dealing with critical production assets in remote environments, the cost of getting it wrong is massive. What we achieved here -detecting an issue with a 100 percent failure likelihood before it happened – is exactly why predictive maintenance matters. It’s not just about technology. It’s about using the right data, reviewed by the right people, at the right time to prevent failures and keep equipment running. That’s what makes the difference.”
Andrew Rayment, Program Manager, Dingo

 

Program Highlights

  • Component Health: Components in critical condition (red) dropped from 18% in November to 2.21% by April. Components in normal (green) and warning (yellow) categories now make up 97.79% of the fleet, indicating significant reliability improvement.

  • High User Engagement: The mobile app saw immediate uptake across departments, enabling real-time reporting and detailed inspections directly from the field. This cross-functional visibility allowed teams—from maintenance to planning—to act on issues faster and with greater coordination. The ability to capture and share data instantly not only improved responsiveness but also increased user buy-in, as teams saw direct impact from their input. With over 5,800 equipment reviews completed, this high engagement became a key driver of early issue detection and contributed significantly to the success of the program.
  • Remote Deployment Success: This deployment, from planning to value realization, was executed entirely remotely, without the need for extended on-site support. Dingo’s model combines centralized expertise, cloud-based technology, and structured workflows to deliver predictive maintenance programs quickly and efficiently, regardless of location. For remote or logistically complex sites, this means faster time to value, minimal disruption to operations, and immediate access to actionable knowledge—proving that scalable, high-impact outcomes don’t require boots on the ground.

 

Conclusion

In just months, Dingo’s remote, data-driven deployment helped this isolated gold mine avoid over $3 million in breakdown-related costs, including a major save on critical production equipment. By centralizing thousands of condition data points in TRAKKA and applying expert analysis, Dingo enabled early risk detection, swift interventions, and measurable improvements in asset health with no on-site implementation required.

“At Dingo, we believe in delivering measurable value. With the right combination of people, tools, and expertise, we help our customers realize results — millions in savings in this case — within weeks, not months. But speed alone is not enough. Our goal is sustained value over the long term, which requires ongoing partnership, continuous optimization, and a shared commitment to keeping critical assets healthy and productive. It’s the people, Dingo and our clients, alongside smart technology and proven processes, who make that possible.”
Craig Banks, Chief Operating Officer, Dingo